Here's a view of the progress at the new Bancroft Elementary School at Bancroft and Pemberton Roads. Workers were even there on a recent chilly Saturday morning. According to the Kennett Consolidated School District's website, work is ahead of schedule:
"The building is shaping up - most of the exterior walls are complete or underway, and flooring is started in the lower levels. Geothermal piping has been run to the mechanical room area, and the spray insulation is being added. The goal is to have the building "under roof" before the end of December to allow interior work to continue through the more severe winter weather."